HGCAL Rentrée General Meeting August 2024

https://indico.cern.ch/event/1432891/

Intro and Overview:

HGCRocs:

  • v3b: ~1k chips (ordered more 25 wafer => 10% total this summer for module pre-production)
  • v3c: 30% (75 wafers) ordered end of 2024

Schedule (P.Bloch)

  • The schedule is currently driven by HGCROC availability
  • If the HGCROC v3C recently submitted is satisfactory, will do 75 by end of year
  • unclear whether ROC3B is suitable for HDs
  • have to confirm the PLL radiation issue (not corrected in ROC3C) can be coped with for highly irradiated modules such as the 120um HDs

Modules

https://indico.cern.ch/event/1432891/contributions/6028472/attachments/2916926/5119078/Kyre_HGC_RENTREE_28Aug2024.pdf

  • Irradiation of Partials
    • C-Fiber likely to be ok for the CE-H
  • UCSB 5 LR-R modules with Ti baseplates (50Mrad irradiation planned)
  • Ideas for addressing ESD vulnerabliity:
    • Shunt HV to GND for handling and module building, remove for testing – CERN/UMN looking into this –
    • Encapsulate the exposed metal on the common mode capacitors. Has advantage that can easily be added as a step in the industrial final assembly.
  • Investigating new expoxy patter:
    • No epoxy on the periphery near GR (noisy channels fix)
    • Encapsulate exposed common mode capacitors on hexaboard with paths to HGCROC (ESD fix)
  • Schedule:
    • Sep: Finish pre-series modules
    • Oct: 2 modules per day x 1 week (one gantry tray)
    • Nov-Dec: 4 modules per day x 1 week (one gantry tray)
    • March 4 / day x 3 days (w/new trays)
    • April 8/ day x 3
    • May 12/day x 3

Follow-ups